Concrete & Building · Field Guide

How Much Concrete Do I Need? A Complete Estimating Guide

Updated August 2026 7 min read MyHouseLogic Editorial
Units:

Dual figures like 2–4 in (50–100 mm) follow this setting — and every calculator on MyHouseLogic uses it too.

Running short of concrete halfway through a pour is one of the most consequential arithmetic mistakes in home improvement: the truck leaves, the placed portion starts setting, and the only fixes are a cold joint or a second delivery with its own minimum load. Ordering far too much carries its own penalty — ready-mix suppliers bill for what you order, not what you place.

The math itself is forgiving: volume is length × width × depth, converted to cubic metres or bags. What trips people up is unit consistency, the volume posts displace, and the waste allowance separating a clean pour from a short one. Every example below matches the math our Concrete Slab & Footing Calculator performs.

Quick answer

Volume is length × width × depth, all in metres, giving cubic metres (1 m3 = 1,000 litres = 1.30795 yd3). A 3 × 3 m slab at 100 mm thick is 0.9 m3; with a 10% waste allowance that is 1.0 m3 — about 85 twenty-five-kilo bags. Allow 5% waste on flatwork, 10% on footings and irregular shapes, 15% on small pours under 1 m3. Run exact dimensions through the Concrete Slab & Footing Calculator — it applies these same constants and rounds bags up for you.

The Volume Formula, and the Two Conversions That Matter

Every concrete estimate starts as a rectangular box: length × width × depth, all three in the same unit. The classic error is depth — forms are built in millimetres, but the formula wants metres: 100 mm becomes 0.10 m, 125 mm becomes 0.125 m, 150 mm becomes 0.15 m. Metres × metres × metres gives cubic metres, the unit ready-mix plants and bag yields are quoted in.

Two conversions carry cubic metres into the real world. One is litres: 1 m3 = 1,000 L, the unit bag yields are printed in. The other is cubic yards for suppliers who sell by the yard: 1 yd3 = 27 cu ft = 0.7646 m3. The working constants this article and the calculator share:

Quantity Working value
1 cubic metre = 1,000 litres = 1.30795 yd3
55.1 lb25 kg bag (common metric size) yields ≈ 11.7 litres of mixed concrete
25 kg bag (80 lb in North America) yields ≈ 0.60 cu ft17 litres
1 cubic metre in bags ≈ 86 twenty-five-kilo bags, or 59 eighty-pound bags

Worked Example: A 3 × 3 Metre Slab at 100 mm

The standard example — the same one the calculator uses — is a 3 × 3 m slab, 100 mm thick. Length and width are already metres; depth converts as 100 ÷ 1000 = 0.10 m. Volume is 3 × 3 × 0.10 = 0.9 m3 (1.18 yd3).

Now add waste. For a small hand-poured slab, 10% is a safe planning allowance: 0.9 × 1.10 = 0.99 m3 — call it 1.0 m3. In bags: 990 litres ÷ 11.7 = 84.6, rounding up to 85 twenty-five-kilo bags; in eighty-pound bags (17 litres each), 990 ÷ 17 = 58.2, rounding up to 59 bags. Bag yields differ by brand — when the yield printed on your bag is not 11.7 litres, the calculator's bag-yield field takes your number and the count follows it.

That bag count is the honest part of the arithmetic: 85 twenty-five-kilo bags is more than two tonnes to mix, haul, and place in one session. Somewhere between 1 and 1.5 m3, ready-mix delivery becomes more practical and saner than bags.

Footings: Continuous Trenches and Pad Footings

A continuous footing is a long, narrow box — trench length × width × depth, all in metres. A perimeter footing running 18 m at 300 mm wide and 200 mm deep is 18 × 0.3 × 0.2 = 1.08 m3; with 10% waste, order about 1.2 m3 rounded to the supplier's convenience. If the footing steps down a slope, calculate each run separately — depth changes along the trench.

Pad footings — the isolated squares under posts and columns — are a counting exercise: calculate one pad's volume (length × width × depth) and multiply by the number of pads. Six pads at 600 × 600 mm and 300 mm deep are 0.108 m3 each, 0.65 m3 total, before waste. Footings are structural elements with code-required dimensions — sizes come from your local building authority or a design; this section is only the arithmetic for whatever they specify.

Post Holes: Cylinders, Minus the Post

A post hole is a cylinder: π × radius2 × depth, radius and depth in metres, times the number of holes. The step everyone forgets is subtracting the volume the post displaces — concrete fills the annular gap, not the whole hole.

One common case: a 300 mm-diameter hole, 900 mm deep. Radius = 0.15 m, so the hole is π × 0.152 × 0.9 = 64 litres. A 90 × 90 mm post displaces roughly 7 litres over that depth, leaving about 57 litres of concrete — 57 ÷ 11.7 ≈ 4.9, so allow five 25 kg bags per hole. A smaller 200 mm-diameter, 600 mm-deep hole with the same post holds roughly 14 litres net — about one 25 kg bag with a little spare, the classic fence-post rule of thumb. Twenty holes at the bigger size is about 1.1 m3; multiply before you buy, not after you start.

Irregular Shapes: Divide and Average

Odd footprints surrender to two tactics. Division: split an L-shaped patio into two rectangles, estimate each, add them. Averaging: for shapes that taper or curve gently, average the widest and narrowest widths and multiply by length — a walk running 1 m to 1.5 m wide over 7 m is treated as 1.25 × 7 = 8.75 m2. Both trade a little precision for speed, and the waste allowance covers the trade. True curves use the circle formulas — π r2 for area, times depth.

One more scaling rule: thickness decisions belong to the slab thickness guide, but volume scales linearly with depth — every extra 25 mm on a 3 × 3 m slab adds 0.225 m3 — about 19 more 25 kg bags.

Waste Allowances: How Much Extra to Figure

Waste is not sloppiness — it is spillage, over-excavation, a subgrade that dips 25 mm low, and the heel of concrete left in the mixer. The site's planning numbers: 5% for flatwork on well-prepared ground, 10% for footings and anything irregular, and 15% for small pours under 1 m3, where one spilled batch wrecks the whole percentage. On ready-mix orders, convert the allowance into the advice every supplier gives: order about a quarter of a cubic metre beyond the calculated total.

Bags or Ready-Mix? Ordering Decisions

Bagged concrete needs no delivery and stops at exactly the count you need — but every bag must be mixed, and 80-plus bags is a full crew day. Ready-mix arrives mixed, consistent and in any volume, with the mixing already done.

Most ready-mix plants have a minimum load, commonly around 1 m3, and charge a short-load fee below about 2–3 m3. That fee is why the break-even against bags lands in the 1–1.5 m3 range: below it, bags usually win; above it, the truck wins on mixing labour, your back, and finish quality. When you call, quote the cubic metres plus the 0.25 m3 safety margin, specify the mix (the supplier can batch to a specification — see our concrete mix ratios guide), and ask about air entrainment for freezing winters.

One planning constraint: concrete sets on its own schedule. A cold joint — the weak plane where fresh concrete meets concrete that has already set — is what you get when a pour stops mid-slab and restarts an hour later. If you must stage a pour, plan the break at a control joint or form edge.

Common Mistakes

  • Mixing units at the depth step. Multiplying 3 × 3 × 100 gives a number 1,000× too big — millimetres snuck into a metres formula. Convert depth to metres first, every time.
  • Ordering the net volume. The net volume assumes perfectly braced forms on a perfectly flat subgrade, neither of which exists.
  • Counting bags by weight instead of yield. A 20 kg and a 25 kg bag are not interchangeable — divide volume by yield (9.5 vs 11.7 litres), then round up.
  • Forgetting the post displaces concrete. Hole volume overstates what you need — subtract the post, especially across dozens of fence holes.
  • Stopping a pour mid-slab. The cold joint between this morning's concrete and this afternoon's is a permanent weak plane — stage at joints or edges by plan.
  • Estimating a thickened-edge slab as a flat box. The thickened perimeter needs its extra volume counted, or the pour runs short exactly where it matters most.

Plan It With the Concrete Slab & Footing Calculator

Calculator connection

The Concrete Slab & Footing Calculator runs this guide's math in one pass: dimensions in; cubic feet, yards, and meters out; bags rounded up; a rebar grid estimate; and your waste factor applied — the same constants, without the long division.

Open the Concrete Slab & Footing Calculator

Frequently Asked Questions

How many 25 kg bags of concrete make a cubic metre?

Eighty-six. A cubic metre is 1,000 litres, a 25 kg bag yields about 11.7 litres, and 1,000 ÷ 11.7 ≈ 86; in eighty-pound bags (17 litres each), the same metre takes 59. Hand-mixing 86 bags is a full day — which is why the cubic metre, not the bag, is the ordering unit beyond small pours.

How much concrete do I need for a 3 × 3 metre slab?

At 100 mm thick, 3 × 3 × 0.1 = 0.9 m3, or 1.0 m3 with a 10% waste allowance — about 85 twenty-five-kilo bags. Thickness scales the result linearly: at 125 mm the same slab needs 1.13 m3 net, 1.24 with waste.

Can I pour a slab in two stages?

Not as one monolithic slab. Once concrete sets, the next batch bonds only weakly to it — that interface is a cold joint, a built-in weak plane. If staging is unavoidable, plan the break at a control joint or an edge and finish each stage separately; two separated pours beat one interrupted pour.

How much extra concrete should I order?

Figure 5% waste on flatwork over prepared ground, 10% on footings and irregular shapes, and 15% on small pours under a cubic metre. On ready-mix deliveries, that translates into the standard advice: order about a quarter of a cubic metre beyond the calculated volume. A little leftover is a minor nuisance; a short pour is a cold joint.

How many bags of concrete per fence post?

It depends on the hole. A 200 mm-diameter, 600 mm-deep hole with a 90 × 90 mm post holds roughly 14 litres of concrete — one 25 kg bag. A 300 mm-diameter, 900 mm-deep hole holds about 56 litres net of the post — roughly five bags. Compute the cylinder (π × radius2 × depth), subtract the post, divide by 11.7 litres.

Related MyHouseLogic Guides

Volume is the middle of the concrete plan — thickness and mix come first, curing and steel follow.

The bottom line: multiply in feet, divide by 27, subtract what the posts displace, and add waste for the pour you will actually run. The yard is the ordering unit, the bag is the mixing unit, and the quarter-metre margin on every truck order is better insurance than any cold joint.