Concrete Slab & Footing Calculator

Estimate cubic metres and cubic yards, 25 kg / 80 lb bag counts and #4 rebar requirements — including a waste factor. Built for patios, driveways, footings, shed pads and walkways, in metric and imperial units.

What you'll need before you start
  • A tape measure, and the length and width of your slab area
  • Your planned thickness (4 in. patios, 5–6 in. driveways — the guide below helps)
  • A rough idea of rebar spacing, or set it to 0 to skip steel
  • The bag sizes your supplier sells (25 kg and 80 lb are both covered)

Enter Your Measurements

All measurements update results instantly. Toggle Met/Imp in the header.

m
m
cm — e.g. 100 mm patio, 150 mm driveway
cm — set 0 to skip rebar
% added to total volume
Your Results Reference: ASTM C143, ACI 318
Cubic Yards
with waste
0
Cubic Meters
m³
0
25 kg Bags
pre-mixed
0
80 lb Bags
pre-mixed
0
Rebar Pieces
#4 grid
0
Rebar Length
linear
0
Total Concrete Required 0
Slab footprint with rebar grid layout (orange). Resize inputs to update.
Freshly poured concrete slab in wooden formwork with a wet surface sheen and rebar grid exposed at the edge
A fresh pour in wooden formwork — rebar at the edge, surface floated and curing.

What Your Results Mean

Start by measuring the longest side of your slab — this is your length. Then measure the perpendicular side for width. For thickness, residential patios and walkways are typically poured at 100 mm (4 in), driveways at 125–150 mm (5–6 in), and footings from 200 to 300 mm (8–12 in) — all varying with local building regulations and soil bearing capacity. If you're unsure about thickness, consult your local building authority or a qualified contractor; undersized slabs crack under load.

For the rebar spacing field, 400 mm (16 in) on centre is a common residential grid for 100 mm slabs, while 600 mm (24 in) on centre is acceptable for lighter-duty applications like shed pads. Set the value to 0 if you're pouring fibre-reinforced concrete without rebar, or if you're using welded wire mesh instead. The calculator assumes 12 mm (#4 / half-inch) bar, a common residential size — bar designations and stock lengths vary by country, so ask your supplier what is available locally.

Waste factor accounts for spillage, over-excavation, and uneven subgrade. Five percent is fine for large flat pours on prepared ground; ten percent is a safe default for footings and irregular shapes; fifteen percent is wise for small pours under one cubic metre where a single overfill ruins your math. When in doubt, round up — running out of concrete mid-pour is far worse than one extra bag.

What the Results Mean

  • Cubic Metres / Cubic Yards: The total adjusted volume. Order this amount from a ready-mix supplier for pours over about 1.5 cubic metres (2 cubic yards).
  • 25 kg / 80 lb Bags: Pre-mixed bag counts for hand pours, in the two common retail standards. A 25 kg bag yields approximately 11.7 litres (0.0117 m³); an 80 lb bag yields approximately 17 litres (0.60 cubic feet). Yields vary slightly by brand — check the bag.
  • Rebar Pieces: Total number of grid pieces required, in both directions — cut from standard stock lengths (which vary by country).
  • Rebar Length: Total linear length of steel needed. Useful if you buy by the bundle rather than per-stick.
  • Total Concrete Required: The waste-adjusted volume in both unit systems — the single number to read out to a ready-mix supplier.

Ordering from a Ready-Mix Supplier

For pours larger than about 1.5 cubic metres (2 cubic yards), ready-mix delivery is usually the practical choice over bagged concrete and dramatically easier on your back. Most ready-mix companies have a minimum load and charge a short-load fee below about 3 cubic metres. When you call, give them the volume shown in this calculator plus a little extra for safety. Specify the slump (100 mm / 4 in is standard for flatwork, 125–150 mm / 5–6 in for footings with rebar), and ask about air entrainment if you live in a freeze-thaw climate.

Pro Tip

Ready-mix trucks are 2.5 to 3 metres wide and need at least 4 metres of vertical clearance. If your site can't fit a truck, plan for wheelbarrows or a concrete pump — pumping is an extra logistics step to arrange in advance.

The Math Behind the Calculator

Concrete volume is fundamentally length × width × depth. In metric the units line up directly: metres × metres × metres gives cubic metres. If you measure in feet, multiply to cubic feet and divide by 27 for cubic yards (1 cubic yard = 27 cubic feet); 1 cubic metre = 1.30795 cubic yards.

volume_m³ = length_m × width_m × depth_m
volume_yd³ = volume_ft³ ÷ 27
volume_with_waste = volume × (1 + waste% / 100)

Bag Yield Reference

Pre-mixed bag yields are published by manufacturers. Bag sizes differ by region — use the yield for the bag your supplier actually sells:

  • 25 kg bag (common metric size) — approximately 11.7 litres (0.0117 m³)
  • 20 kg bag (common in Australia and New Zealand) — approximately 9.5 litres
  • 40 kg bag (common in Canada) — approximately 19 litres
  • 40 / 60 / 80 / 90 lb bags (US sizes) — approximately 0.30 / 0.45 / 0.60 / 0.68 cubic feet (8.5–19 litres)

To convert volume to bags, divide by the yield for your bag. For example, 0.10 m³ ÷ 0.0117 = 8.5, so 9 bags of 25 kg mix. Always round up — you cannot buy nine-tenths of a bag.

Rebar Grid Calculation

Rebar layout is a two-direction grid. The number of pieces running along the length equals the number of width-wise segments plus one (because both ends need a piece). Same goes for the width direction. Mathematically (in any consistent unit):

pieces_along_length = ceil(length / spacing) + 1
pieces_along_width = ceil(width / spacing) + 1
total_pieces = pieces_along_length + pieces_along_width

Each piece running along the length has a length equal to the slab width, and vice versa. Multiply and sum to get total linear length.

Assumptions & Limitations

Every number above rests on these constants. If your project differs, change the matching input — or read the linked guide for the full reasoning.

  • 25 kg bag yields 0.0117 m³ (11.7 L); 80 lb bag yields 0.60 cu ft (17 L) — manufacturer published values
  • 12 mm (#4) rebar grid, counted in both directions — bar sizes and stock lengths vary by country
  • Waste factor is added to volume before bags are calculated
  • Quantities only — this site deliberately does not price labour, delivery or materials

Worked Example: 6×4 Metre Driveway Apron

Let's walk through a real pour. Suppose you're pouring a 6 by 4 metre driveway apron at 150 mm thick, with 12 mm (#4) rebar on a 400 mm grid, and you want a 10 percent waste factor. Plug these into the calculator and watch what happens:

  1. Volume: 6 × 4 × 0.15 = 3.6 cubic metres (4.7 cubic yards).
  2. With 10% waste: 3.6 × 1.10 = 3.96 cubic metres — call it 4.0 m³ (5.2 yd³) when ordering.
  3. Bags: 3.96 m³ ÷ 0.0117 = 339 twenty-five-kilo bags (or 234 eighty-pound bags). That's a lot of mixing — this is exactly where ready-mix delivery becomes the practical choice.
  4. Rebar: ceil(6 ÷ 0.4) + 1 = 16 pieces running width-wise, plus ceil(4 ÷ 0.4) + 1 = 11 pieces running length-wise. Total = 27 pieces, cut from standard stock lengths.
  5. Linear steel: (16 × 4 m) + (11 × 6 m) = 64 + 66 = 130 linear metres.

For comparison, the same pour is about 5.2 cubic yards from a ready-mix truck — one delivery instead of hundreds of bags and an entire weekend of mixing. The calculator gives you the volumes; the bags-versus-truck decision follows from them.

Reminder

The quantities exclude forms, stakes, vapor barrier, fill and finishers' labour. Treat the results as a materials checklist to take to your supplier, not a turnkey plan.

Frequently Asked Questions

How many bags of concrete make a cubic yard?

One cubic yard (0.76 m³) takes about 77 twenty-five-kilo bags (each yielding 11.7 litres) or 45 eighty-pound bags (each yielding 0.60 cu ft). For any pour over 1.5 cubic metres, ready-mix delivery is usually more practical than bag mixing.

What waste factor should I use for concrete?

Use 5% for flat work on prepared ground, 10% for footings and irregular shapes, and 15% for small pours under one cubic metre where any spillage has an outsized impact. Always err on the side of more — running out mid-pour causes cold joints.

How thick should a concrete slab be?

Residential patios and walkways: 100 mm (4 in). Driveways: 125–150 mm (150 mm if you park heavy vehicles). Shed pads: 100–150 mm depending on shed size. Footings: 200–300 mm minimum depending on local regulations and soil bearing capacity. Always verify with your local building authority.

Do I really need rebar in a 100 mm slab?

For residential patios and walkways on well-compacted subgrade, fibre-reinforced concrete often eliminates the need for rebar. For driveways, slabs larger than about 10 m², or any slab bearing loads, 12 mm (#4) rebar on a 400 or 600 mm grid significantly reduces shrinkage cracking and improves load distribution.

Can I pour concrete in cold weather?

Yes, but concrete must be protected from freezing for the first 24 hours minimum. Use hot water in the mix, thermal blankets, and consider air-entrained concrete. Avoid pouring when ambient temperature is below −7°C (20°F). See our concrete curing guide for the full protocol.

Should I order ready-mix or use bags?

Roughly 1.5 cubic metres (2 cubic yards). Below that, bags are practical; above it, ready-mix saves a weekend of mixing. Bag yields are printed on the bag — a 25 kg bag yields about 11.7 litres, an 80 lb bag 0.60 cu ft — so the calculator converts your volume into either standard.

Total Required
—
View Details