Concrete Slab & Footing Calculator

Estimate cubic yards, cubic meters, 60 lb / 80 lb bag counts, #4 rebar grid requirements, and total material cost — including a waste factor. Built for patios, driveways, footings, shed pads, and walkways.

Enter Your Slab Dimensions

All measurements update results instantly. Toggle Imperial/Metric in the header.

ft
ft
in — e.g. 4" patio, 6" driveway
in — set 0 to skip rebar
% added to total volume
USD — adjust for your supplier
USD — typical 1/2" #4 rebar price
Estimated Materials ASTM C143 · ACI 318
Cubic Yards
with waste
0
Cubic Meters
0
60 lb Bags
pre-mixed
0
80 lb Bags
pre-mixed
0
Rebar Pieces
#4 grid
0
Rebar Length
linear
0
Estimated Total Cost $0.00
Slab footprint with rebar grid layout (orange). Resize inputs to update.

How to Use This Concrete Calculator

Start by measuring the longest side of your slab — this is your length. Then measure the perpendicular side for width. For thickness, residential patios and walkways are typically poured at 4 inches, driveways at 5 to 6 inches, and footings vary from 8 to 12 inches depending on local building code and soil bearing capacity. If you're unsure about thickness, consult your local building department or a licensed contractor; undersized slabs crack under load.

For the rebar spacing field, 16 inches on center is the most common residential grid for 4-inch slabs, while 24 inches on center is acceptable for lighter-duty applications like shed pads. Set the value to 0 if you're pouring fiber-reinforced concrete without rebar, or if you're using welded wire mesh instead. The calculator assumes #4 rebar (1/2-inch diameter), which is the standard for residential flatwork.

Waste factor accounts for spillage, over-excavation, and uneven subgrade. Five percent is fine for large flat pours on prepared ground; ten percent is a safe default for footings and irregular shapes; fifteen percent is wise for small pours under one cubic yard where a single overfill ruins your math. When in doubt, round up — running out of concrete mid-pour is far more expensive than buying one extra bag.

What the Results Mean

  • Cubic Yards / Cubic Meters: The total adjusted volume. Order this amount from a ready-mix supplier for pours over 1.5 cubic yards.
  • 60 lb / 80 lb Bags: Pre-mixed bag counts for hand pours. An 80 lb bag yields approximately 0.60 cubic feet of cured concrete; a 60 lb bag yields approximately 0.45 cubic feet.
  • Rebar Pieces: Total number of 10-foot #4 sticks required to build the grid, including cross pieces in both directions.
  • Rebar Length: Total linear length of steel needed. Useful if you buy by the bundle rather than per-stick.
  • Total Cost: Bags at your input price plus rebar at your input price per stick. Does not include delivery, forms, vapor barrier, or finishing labor.

Ordering from a Ready-Mix Supplier

For pours larger than 1.5 cubic yards, ready-mix delivery is almost always cheaper than bagged concrete and dramatically easier on your back. Most ready-mix companies have a one-yard minimum load and charge a short-load fee below 3 yards. When you call, give them the cubic yards shown in this calculator plus an extra quarter yard for safety. Specify the slump (4 inches is standard for flatwork, 5 to 6 inches for footings with rebar), and ask for air entrainment if you live in a freeze-thaw climate.

Pro Tip

Ready-mix trucks are 8 to 10 feet wide and need at least 14 feet of vertical clearance. If your site can't fit a truck, plan for wheelbarrows or a concrete pump — pumps typically add $300 to $500 to the job.

Advertisement

The Math Behind the Calculator

Concrete volume is fundamentally length × width × depth. The trick is unit consistency: multiply in feet and divide by 27 to get cubic yards (because 1 cubic yard = 27 cubic feet), or multiply by 0.0283168 to get cubic meters.

volume_cubic_ft = length_ft × width_ft × depth_ft
volume_cubic_yd = volume_cubic_ft ÷ 27
volume_cubic_m = volume_cubic_ft × 0.0283168
volume_with_waste = volume × (1 + waste% / 100)

Bag Yield Reference

Pre-mixed bag yields are published by manufacturers and confirmed by ASTM standards:

  • 40 lb bag — approximately 0.30 cubic feet
  • 60 lb bag — approximately 0.45 cubic feet
  • 80 lb bag — approximately 0.60 cubic feet
  • 90 lb bag — approximately 0.68 cubic feet

To convert cubic feet to bags, divide by the yield. For example, 5.4 cubic feet ÷ 0.60 = 9 bags of 80 lb mix. Always round up — you cannot buy nine-tenths of a bag.

Rebar Grid Calculation

Rebar layout is a two-direction grid. The number of pieces running along the length equals the number of width-wise segments plus one (because both ends need a piece). Same goes for the width direction. Mathematically:

pieces_along_length = ceil(length_ft / spacing) + 1
pieces_along_width = ceil(width_ft / spacing) + 1
total_pieces = pieces_along_length + pieces_along_width

Each piece running along the length has a length equal to the slab width, and vice versa. Multiply and sum to get total linear feet.

Worked Example: 20×16 Driveway Apron

Let's walk through a real pour. Suppose you're pouring a 20 by 16 foot driveway apron at 6 inches thick, with #4 rebar on a 16-inch grid, and you want a 10 percent waste factor. Plug these into the calculator and watch what happens:

  1. Volume: 20 × 16 × (6÷12) = 160 cubic feet = 5.93 cubic yards.
  2. With 10% waste: 5.93 × 1.10 = 6.52 cubic yards. Round up to 6.6 yards for ordering.
  3. Bags: 160 × 1.10 = 176 cubic feet ÷ 0.60 = 294 eighty-pound bags. That's a lot of mixing — this is exactly where ready-mix delivery becomes economical.
  4. Rebar: ceil(20÷1.33)+1 = 16 pieces running width-wise, plus ceil(16÷1.33)+1 = 13 pieces running length-wise. Total = 29 pieces of 10-foot #4 rebar.
  5. Linear feet of steel: (16 × 16) + (13 × 20) = 256 + 260 = 516 linear feet.
  6. At $6.50 per 80 lb bag: 294 × $6.50 = $1,911 in bagged concrete alone. At $7.00 per rebar stick: 29 × $7.00 = $203. Total materials: $2,114.

For comparison: a ready-mix delivery of 7 yards at $145 per yard = $1,015, plus the same $203 in rebar = $1,218. On this pour, ready-mix saves nearly $900 and an entire weekend of mixing. The calculator gives you the numbers to make that call.

Reminder

The cost figure excludes forms, stakes, vapor barrier, fill, finishers' labor, and any pump fee. Treat it as a materials-only budget line, not a turnkey bid.

Frequently Asked Questions

How many bags of concrete make a yard?

One cubic yard equals 27 cubic feet. That requires 60 sixty-pound bags (each yielding 0.45 cu ft) or 45 eighty-pound bags (each yielding 0.60 cu ft). For any pour over 1.5 cubic yards, ready-mix delivery is typically cheaper and faster than bag mixing.

What waste factor should I use for concrete?

Use 5% for flat work on prepared ground, 10% for footings and irregular shapes, and 15% for small pours under one cubic yard where any spillage has an outsized impact. Always err on the side of more — running out mid-pour causes cold joints.

How thick should a concrete slab be?

Residential patios and walkways: 4 inches. Driveways: 5 to 6 inches (6 if you park heavy trucks). Shed pads: 4 to 6 inches depending on shed size. Footings: 8 to 12 inches minimum depending on local code and soil bearing capacity. Always verify with your local building department.

Do I really need rebar in a 4-inch slab?

For residential patios and walkways on well-compacted subgrade, fiber-reinforced concrete often eliminates the need for rebar. For driveways, slabs larger than 100 sq ft, or any slab bearing loads, #4 rebar at 16" or 24" on center significantly reduces shrinkage cracking and improves load distribution.

Can I pour concrete in cold weather?

Yes, but concrete must be protected from freezing for the first 24 hours minimum. Use hot water in the mix, thermal blankets, and consider air-entrained concrete. Avoid pouring when ambient temperature is below 20°F (-7°C). See our concrete curing guide for the full protocol.

Should I order ready-mix or use bags?

The break-even point is roughly 1.5 cubic yards — below that, bags are practical; above it, ready-mix saves money and labor. A typical 80 lb bag costs $6–$8 and yields 0.60 cu ft, so 1 cubic yard of bagged mix costs roughly $270–$360 plus your time. Ready-mix is typically $130–$170 per yard including delivery.

Total Estimate
View Details