Mortar Calculator & Mix Ratios

Cement and sand for any volume of mortar at any ratio from 1:3 to 1:6 — 25 kg bags of cement, sand in kilograms and cubic metres, with the dry-volume factor and waste built in. Pairs directly with the brick & block calculator.

What you'll need before you start
  • The finished (wet) mortar volume you need — from the brick & block calculator's mortar row
  • Your mix ratio — 1:3 strong through 1:6 lean, chosen for the job (see below)
  • Your waste figure — 10% is a typical default for mixed and placed mortar
  • The bag size your cement comes in — this tool works in 25 kg bags

Enter Your Measurements

All measurements update results instantly. Toggle Met/Imp in the header.

m³ finished, wet volume
% added for mixing and placement losses
Your Results Standard constants — 1.33 dry factor
Cement
kilograms
0
Cement Bags
25 kg bags, rounded up
0
Sand
kilograms, dry loose
0
Sand Volume
m³, dry loose
0
Total Materials Required 0

How to Use the Mortar Calculator

Start with the volume of finished mortar you need — the wet material that actually ends up in the joints. The easiest source is the brick & block calculator: enter your wall, take its mortar row, and type that figure here. Working by hand, the joint volume approach gives the same answer: joint cross-section (roughly unit depth × joint thickness, allowing for perpends) times total joint length. Typical trade figures land near 0.026 m³ of mortar per m² of metric brickwork and 0.012 m³ per m² of blockwork at a 10 mm joint.

The ratio is cement to sand by volume. Typical practice — and it does vary by country, tradition and the units being laid — runs roughly like this: 1:3 for very strong, exposed work and below damp-proof course in some traditions; 1:4 for general-purpose strong work; 1:5 for everyday bricklaying; 1:6 for internal lightweight blockwork, where a strong mix is harder than the block itself and cracks across the joints. Modern practice replaces the lime that older mixes used with a liquid plasticiser at around a capful per batch, which makes 1:5 and 1:6 mixes workable without lime. Block manufacturers publish recommended mortars for their products — follow those where they exist.

Why the arithmetic is not just "volume divided by parts": dry ingredients and finished mortar occupy different volumes. When you mix cement and sand with water, the cement paste fills the voids between sand grains, and the finished mortar comes out at roughly three-quarters of the dry ingredients' bulk. So one cubic metre of finished mortar needs about 1.33 m³ of dry ingredients — a standard trade factor, and the source of the constant in the formula below. The waste factor then covers what stays in the mixer, the bucket and the wheelbarrow; 10% is a typical default.

Mass follows from two standard constants: cement at 1440 kg/m³ and sand at 1600 kg/m³, both loose bulk densities the trade uses for ordering. One cubic metre of mortar at 1:4 therefore works out to about 383 kg of cement — call it 16 bags of 25 kg — and about 0.44 m³ of sand. A richer 1:3 mix takes about 479 kg (roughly 20 bags) and a leaner 1:6 about 274 kg (11 bags); the sand share moves the other way. Your actual cement may come in 94 lb (42.6 kg) sacks if you are in the US — divide the kilogram figure accordingly.

Two honest limits. First, this is a cement-and-sand tool: lime mortars for older buildings are a different material, gauged on putty or hydraulic lime, and the supplier's guidance beats any generic calculator. Second, mortar is not concrete — it has no coarse aggregate, and using it as one is a false saving. For slabs and footings, see the mortar mix ratios guide for the full background, or the concrete mix ratios guide for the structural stuff.

The Math Behind the Calculator

Three steps: inflate the wet volume to dry, split it by ratio parts, then convert volumes to masses with standard bulk densities.

dry_volume = volume × 1.33 × (1 + waste% ÷ 100)
parts = 1 + n (n = sand parts in the ratio)
cement_volume = dry_volume ÷ parts
sand_volume = dry_volume × n ÷ parts
cement_kg = cement_volume × 1440
bags = ⌈ cement_kg ÷ 25 ⌉
sand_kg = sand_volume × 1600

The constants are the standard ones the trade uses: 1.33 for the dry-to-wet bulk factor, 1440 kg/m³ for loose bulk cement, 1600 kg/m³ for loose dry sand. Actual densities vary a little by grading and moisture, and bag weights by market — the constants get you within a bag on realistic volumes, which is closer than most batches get mixed.

Worked Example: 0.25 m³ at 1:4

A garden wall from the brick calculator needs 0.52 m³ of mortar; halve that for a shorter wing wall and you have 0.25 m³ to mix at 1:4, allowing 10% waste. Enter volume 0.25, ratio 1:4, waste 10.

  1. Dry volume: 0.25 × 1.33 × 1.10 = 0.366 m³.
  2. Parts: 1 + 4 = 5.
  3. Cement volume: 0.366 ÷ 5 = 0.0732 m³ → × 1440 ≈ 105.4 kg → 105.4 ÷ 25 = 4.2 → 5 bags.
  4. Sand volume: 0.366 × 4 ÷ 5 = 0.293 m³.
  5. Sand mass: 0.293 × 1600 ≈ 468 kg — about nineteen 25 kg bags of dry sand, or roughly half a typical 850 kg bulk bag.

Field check: one cubic metre of 1:4 mortar by the same math is 383 kg of cement — 16 bags — and 0.44 m³ of sand, which matches the trade shorthand that a bulk bag of sand and a dozen-plus bags of cement keep a bricklayer busy for a good stretch. Scale that to 0.25 m³ and you are back to 5 bags and half a bulk bag of sand: consistent.

Assumptions & Limitations

Every number above rests on these constants. If your project differs, change the matching input — or read the linked guide for the full reasoning.

  • Dry factor 1.33 — dry ingredients bulk about a third more than finished wet mortar (standard trade constant)
  • Cement 1440 kg/m³ and sand 1600 kg/m³ loose bulk densities — standard constants; actual loads vary with grading and moisture
  • Cement bags are 25 kg — divide the kg row for other bag sizes (a US 94 lb sack is about 42.6 kg)
  • Waste is applied to the dry volume before splitting by ratio
  • Sand figures are dry loose volume — damp sand bulks and occupies more space per kg
  • Quantities only — no plasticiser, lime, pigments or mixing water scheduled

Frequently Asked Questions

What mortar mix ratio should I use?

Typical practice: 1:3 to 1:4 for strong, exposed or below-DPC work; 1:5 for general bricklaying; 1:6 for internal lightweight blockwork, where the mortar should never be stronger than the units it joins. Practice varies by country and material — follow the block or brick manufacturer's guidance where it exists, and the mix ratios guide for the reasoning.

Why multiply mortar volume by 1.33?

Because dry materials and finished mortar occupy different volumes. When cement, sand and water combine, the paste fills the voids between sand grains and the mix shrinks to roughly three-quarters of its dry bulk — so 1 m³ of finished mortar needs about 1.33 m³ of dry ingredients. It is a standard trade factor used everywhere mortar is batched by volume.

How many 25 kg bags of cement per cubic metre of mortar?

About 16 bags at 1:4 — roughly 383 kg at 1440 kg/m³ cement. A rich 1:3 mix takes about 20 bags (479 kg), 1:5 about 13 (319 kg), and a lean 1:6 about 11 (274 kg). The calculator applies the same constants to whatever volume you enter, waste included.

Is the sand figure wet or dry?

Dry, loose volume — the figure a supplier quotes for a dry load. Damp sand bulks: moist fine sand can occupy a fifth to a third more space than the same dry mass, so a "cubic metre" of damp sand in a shovel-scooped pile is not the same cubic metre. Gauge batches with buckets or gauge boxes and the problem disappears.

Can I use this calculator for lime mortar?

Only as a rough sanity check. Lime putty and hydraulic lime are batched differently — often by volume of putty, or dry lime measured against damp sand — and heritage work depends on matching the existing mortar's softness. For anything old or listed, follow the lime supplier's mix guidance and get the existing mortar analysed if the job is serious.

Total Required
—
View Details