Garden & Outdoor · Field Guide

How Many Pavers Do I Need? Patterns, Base and Sand

Updated September 2026 8 min read MyHouseLogic Editorial
Units:

Dual figures like 2–4 in (50–100 mm) follow this setting — and every calculator on MyHouseLogic uses it too.

A paver project is three separate material orders wearing one name. The pavers themselves get all the attention - the color, the pattern, the Saturday of arranging them in the driveway to see which way the texture reads. But the project's lifespan and its feel underfoot are decided by the two invisible layers underneath: the compacted aggregate base and the thin bedding course the pavers rest on. Under-order the pavers and you make a second trip; under-order the base and you spend years watching the patio settle into the exact shape of the shortcut you took.

This guide does the full takeoff: area measurement, piece counts by paver size, waste by pattern, excavation depth, tonnes of base, cubic metres of bedding sand, and the joint sand that locks it all together. The worked example is a 3.6 × 5.0 m patio - about 194 sq ft18 m² - carried through every layer so the arithmetic pattern is reusable for any footprint.

Quick answer

Pieces = area × per-m² count × (1 + waste). A 200 × 100 mm paver is 50 per m², 200 × 200 is 25, 300 × 300 about 11, 450 × 450 about 4.9. Waste: 5% running bond, 10% 90° herringbone, 15% diagonal/45°, 15–20% circles and radii. Under it: 100–150 mm compacted base (patio), 25 mm bedding sand, 60 mm pavers. Base weighs about 1.7 tonnes per cubic metre.

Step One: The Area

Measure rectangles as rectangles - length × width - and split anything else into rectangles that sum to the real shape. An L-shaped patio is two rectangles; a curved path is a chain of measured widths along the centerline. For curves, measure the width at several points and use the average, because the stone supply yard sells straight lines. A 3-metre circle is πr² ≈ 76 sq ft7.1 m²; a 3.6 × 5.0 m rectangle is 18 m², which is the number this guide carries.

Two measurement details that matter later. First, decide now where the patio's finished edge lands, because the edge is what the base, the excavation and the plastic restraint all need to reach - the pavers don't get to stop where the base does. Second, if the design has a border or soldier course (a row of pavers turned 90° to frame the field), count it separately: borders are cut-heavy and usually consume their own extra material, roughly 5% beyond the field's waste factor.

Piece Count Math

Pavers are bought by the piece, by the bundle and by the pallet, and sized in millimetres - so the arithmetic runs through square metres. Each paver covers its length × width, and a 200 × 100 mm Holland stone covers 0.02 m²:

Paver sizeCoverage (m²)Pieces per m²
7.9 × 3.9 in200 × 100 mm (Holland)0.0250
7.9 × 7.9 in200 × 200 mm0.0425
11.8 × 7.9 in300 × 200 mm0.06≈ 16.7
11.8 × 11.8 in300 × 300 mm0.09≈ 11.1
15.7 × 15.7 in400 × 400 mm0.166.25
17.7 × 17.7 in450 × 450 mm0.2025≈ 4.9
23.6 × 23.6 in600 × 600 mm0.36≈ 2.8

For the worked patio: 18 m² of 200 × 100 mm Holland pavers (the 4 × 8 in stone) in running bond at a 5% waste factor is 18 × 50 × 1.05 ≈ 945 pieces. Pallets are the real purchasing unit - a pallet of 200 × 100 mm Holland typically covers about 120 sq ft11 m², roughly 550 pieces - so the honest order is two pallets, which lands 240 sq ft22 m² of material against 202 sq ft18.9 m² of need. The surplus isn't waste; it's the future cracked paver in year six, because concrete pavers have dye lots too, and a replacement that matches your weathered originals is unobtainable. Ordering by the pallet, lot-matched, with the leftovers stacked in the garage is the professional move.

Waste by Pattern

The pattern decides the cut count, exactly as it does for tile and plank floors. Running bond and stacked grids cut mostly at the perimeter; herringbone cuts at every border intersection at an angle; diagonal layouts and circle kits cut constantly. The percentages below are the standard planning values, and note that herringbone earns its extra cut waste by being the mechanically strongest pattern for driveways - the interlock resists creeping under turning tires in a way running bond does not.

PatternWasteNotes
Running bond / stacked5%Perimeter cuts only; running bond stronger than stacked
Running bond, 45°10–15%Every edge meets at an angle
Herringbone, 90°10%Best mechanical interlock for driveways
Herringbone, 45°15%Border pieces cut twice
Circle kits, radii, fans15–20%Kit-based; keep the template

The Base, By the Numbers

The excavation depth is a sum: paver thickness (60 mm) + bedding sand (25 mm) + base (100–150 mm for patios, 200–300 mm for driveways). A plain patio therefore digs 185 to 235 mm; a driveway in a frost climate can dig 400. The base material is compacted angular aggregate - road base, crusher run, 20-mm minus, names vary by region - and it goes down in 50- to 100-mm lifts, each compacted with a plate compactor before the next. One pass over 250 mm of loose base compacts nothing but the top.

The base order for the worked patio at a mid-range 125 mm of compacted base: 18 m² × 0.125 m = 2.25 m³. Compacted aggregate weighs about 1.7 tonnes per cubic metre (1.4–1.5 tons per cubic yard), so that's ≈ 3.8 tonnes - order 4, because the loose-to-compacted volume loss and the spoilage at the edges are real. The field shortcut: one tonne of compacted aggregate covers roughly 130 sq ft12 m² at 50 mm, which is a fine sanity check for any order. Driveways and persistently wet or clay soils add geotextile fabric under the base, and driveway base in particular benefits from the fabric separating the aggregate from subgrade that would otherwise swallow it.

Bedding and Joint Sand

Between base and pavers goes exactly 25 mm of loose, sharp concrete sand - not 50 mm, not stone dust, not the fine play sand that turns to mush. The ICPI's standard is 25 mm screeded loose, the pavers settled into it by the plate compactor at the end. The quantity is pure volume: 18 m² at 25 mm is 0.45 m³ - about 0.7 tonnes. One cubic metre of sand covers 40 m² at 25 mm, the same unit-volume arithmetic the concrete slab calculator runs.

The joints are filled with polymeric sand - sand with a polymer binder that activates with water and locks the surface against ants, weeds and washout. Coverage is a function of joint width and paver thickness, and the honest planning numbers for typical 3- to 5-mm joints are 60–100 sq ft5.6–9.3 m² per 44 lb20 kg bag: the worked patio takes 2–3 bags. Wide natural-stone joints are a different product class (the "Gator Dust" tier) covering 15–30 sq ft1.4–2.8 m² per bag. The bag's coverage chart is the authority for your exact paver - but buy a spare bag regardless, because a spring touch-up after the first winter is routine, and the color-matching problem is the same as pavers: product lines get discontinued.

Edges, Slopes and the Rest of the Order

Edge restraint keeps the outermost pavers from creeping outward - without it, the pattern opens at the borders within a season or two. It's sold in 2.4- or 3-metre strips, so the worked 3.6 × 5.0 m patio needs 17.2 linear metres: 6 strips. Steel spikes pin it through the bedding into the base, roughly every 300 mm on straight runs and every 150–200 mm on curves. The full accessory list for a paver order, in the order the yard will ask for it: pavers (by pallet), base aggregate (by the tonne), bedding sand (by the cubic metre or tonne), polymeric sand (by bag), edge restraint (by strip), spikes (by box), and geotextile (by roll, for driveways and wet ground).

One last number before the shovel: slope. The finished surface needs 1–2% of fall away from the house - about 20 mm per metre is the field version - and the base must be graded to the same slope, because the bedding layer is only 25 mm thick and can't fix grade. Drainage is also the one requirement that disqualifies the tempting shortcut of paving over a bad slab, since a slab that holds water now will hold water forever under pavers. Measure the fall with a line level and two stakes before a single paver lands; it's the cheapest quarter-hour of the project.

Frequently Asked Questions

How many 200 × 100 mm pavers are in a square metre?

About 50 - a 200 × 100 mm paver covers 0.02 m², and 1 divided by 0.02 is 50. With a typical 3 mm joint the real count runs about 48 to the metre. Neighboring sizes: 200 × 200 mm are 25 per m², 300 × 300 about 11, and 400 × 400 just over 6. In imperial, a 4 × 8 in paver is 4.5 per square foot. Multiply the count by your area and a waste factor before ordering.

How much base do pavers need?

Patios and walkways: 100 to 150 mm of compacted angular aggregate under 25 mm of bedding sand and the 2-3/8 in60 mm paver. Driveways: 200 to 300 mm of base, and 3-1/8 in80 mm pavers. In frost climates and over weak soils, go to the top of those ranges and add geotextile fabric under the base.

How much polymeric sand do I need for an 18 m² patio?

For typical narrow paver joints of 3 to 5 mm, expect roughly 60-100 sq ft5.6-9.3 m² of coverage per 44 lb20 kg bag - so an 18 m² patio takes 2 to 3 bags. Wide stone joints are a different product class and cover only 15-30 sq ft1.4-2.8 m² per bag. Check the manufacturer's coverage chart for your joint width and paver thickness.

Can I lay pavers over an existing concrete slab?

Yes, if the slab is structurally sound and already drains away from the house - lay a thin bedding layer or use adhesive with thin pavers. Two honest caveats: cracks in the slab telegraph through the pavers eventually, and a slab with standing-water spots will still hold water under the new surface. Broken or poorly drained slabs should be removed, not buried.

How thick should pavers be?

2-3/8 in60 mm is the standard residential paver for patios and walkways; driveways want 3-1/8 in80 mm. Thin 1 in25 mm pavers are for overlay-on-slab applications only and can't take vehicle traffic. Thicker pavers also read more substantial at borders and steps.

Planning guidance for residential paver installs. Site conditions rule the base design - clay, high water tables and frost heave change depths, and driveways plus slopes over 8% may need a professional segmental pavement design.

Where to Read Next

The bottom line: order the pavers by piece count and pattern waste, the base by the tonne (three-quarters of a cubic metre per 25 mm of depth over 30 m²), the bedding sand at exactly 25 mm, and the joint sand by the bag with a spare. The pattern gets the compliments; the base depth decides whether it still deserves them in five years.